Joint Rent Group

 Thursday 23 November 2023, 10am via zoom.

Attendees

Frances McGonagle (tenant volunteer),Harry McCormack (tenant volunteer), June Todd (tenant volunteer), Stefan Kristmanns (Housing Development Co-ordinator), John Kerr (Homelessness & Housing Development Manager), Craig Wilson (Building Services Maintenance Manager), Kevin McCrossan ( Housing Operations Co-ordinator), Janice Rainey (Finance Business Partner), Alan Young (Housing Asset & Investment Manager) and Jane Mack (Snr Housing Dev Officer – Tenant Participation).

Welcome and Apologies

Apologies received from Cllr Gurpreet Johal (Housing Convener),Cllr Hazel Sorrell, Nicola Pettigrew (Housing Operations represented by Kevin McCrossan), Martin Feeney (Building Services represented by Craig Wilson) and Laura Ann Paton (HRA Accountant).

Stefan chaired the meeting.

Updates on outstanding actions

Jane shared the updated action sheet on screen and Stefan went through the updates received.

JRG053 – Matrix has not been fully used or updated for 24/25 estimates and budget setting process. Jim McCarron (taking over from Janice Rainey next month) will be reviewing it. The matrix was developed to increase transparency and meet some of the requirements outlined in the HRA Guidance. Is therefore as tool to provide information to tenants about the budget setting process and also outline the influence they can have around budget setting. Any proposed changes should be agreed by JRG.

Action: Jim McCarron asked to brief future JRG around any proposed changes to the Matrix and the rationale for these.

JRG058 – KMcC confirmed that working group aiming to finalise new Tenant Handbook by 31/12/23 and that relet standard will be outlined and incorporated into this.

Action: Kevin will speak to Suzanne Marshall to ensure there is opportunity for tenants to proof read draft to make sure it is tenant friendly.

JRG067- Briefing note not been found – Stefan confirmed it was issued and will check his laptop. John’s view is that a review of the rent model not needed at this time and suggested parking issue for at least a year. Been no complaints raised about the current model and tenants agreed they were happy to park the issue, mark the action as complete and John can bring issue back to the JRG if it needs looked at in future.

JRG069 –Alan has looked at the figures and confirmed that the money spent figure included £600k from the previous year that had been delayed being put thro so didn’t relate to the number of installs stated. Average install costs for boilers have remained as predicted. Install costs include décor costs too. Group happy with explanation and for action to be marked complete.

JRG074 – 22 voids delayed by meter issues. Craig confirmed that figures will vary and Help to Move are helping but still some issues with the actual energy companies. So still some delays but a process is in place and does get monitored. Agreed action is complete and for meter issue number to be added to void performance template so that it can be monitored via that.

JRG075 Agreed happy with written update provided and decants are included on void template and average time tenants are decanted is included.

JRG076 Rent option discussion meetings taken place and rent consultation launched 15/11/23 – action complete.

Updated template for monitoring of void budget performance

Jane shared void template on screen.

Janice ran through the budget figures for the voids – void rent loss has come down. Council Tax not come down as much as fewer longer term voids have been relet. Revenue spend is under budget but on Capital side way over budget. Janice explained that this was mainly due to an increase in void repair costs and any that cost more than £5k get capitalised and as more void costs are above £5k, more being charged to Capital budget. Average void repair costs are £8,346.

Kevin ran through the void performance figures and confirmed that currently have 193 voids so the downward trend is continuing. Average relet time is down to 36.9 days so just out of target and just out of rent loss target. The number of relets completed has increased slightly this month (up to 236 from 228). Have a new report to help monitor decants and that as well as improved communication between Housing Ops and Building Services has reduced average times and this should continue as they get prioritised.

Décor voucher pilot now being extended to Dumbarton and Alexandria and helping to reduce relet times and give tenants more choice on décor – spending on vouchers is being monitored.

Update on Capital Programme

Jane shared updated Capital programme (Period 5) on the screen.

Alan confirmed that all programmes are on track and Enhance Capital Investment Programme due to deliver the numbers outlined:

  • roof programme slightly down due to need to correspond with owners to get agreement - causes delays but will get done;
  • increase in number of new windows being installed due to additional window contractor.

Tenants happy with progress of Capital programme but doesn’t include the CCTV upgrades which is part of the Enhanced Capital programme. John confirmed that surveys of existing equipment was underway and that should be a programme of work developed by end of January. Tenants keen that progress is monitored so once programme of work available will be shared with JRG and then progress monitored at meetings.

Buybacks are the other aspect of the Enhanced Capital Programme but numbers are already included in the Capital programme template.

Discussion around frequency of updates being provided to JRG and Alan advised that this information must be provided to Council or Housing Committee in advance of being shared with tenants. Next update (Period 7) is due to be provided to Council on 20 Dec 2023 so aim is to provide this update to the JRG early in the new year (so they can discuss at first meeting of 2024).

Date of next meetings

Tenant JRG 30 November, 10 am on zoom

Agreed to keep meetings on Thursdays, 10 am and on zoom – Jane and Harry will co-ordinate WDTRO committee meetings and WDC/WDTRO Liaison meeting dates and then fit in the JRG meetings for 2024.

Joint Rent Group

 Thursday 28 September 2023, 10am via zoom.

Attendees

Cllr Gurpreet Johal ( Housing Convener), Harry McCormack (tenant volunteer), John Kerr ( Homelessness & Housing Development Manager , Nicola Pettigrew ( Housing Operations Manager), Laura Ann Paton ( HRA Accountant), Alan Young ( Housing Asset & Investment Manager), Martin Feeney ( Building Services Manager) and Jane Mack (Snr Housing Dev Officer).

Welcome and apologies

Apologies from Frances McGonagle, June Todd and Stefan Kristmanns

Updates on outstanding actions

Jane shared updated action sheet on screen and went through the updates received.

JRG053 – matrix being used for 24/25 estimates and will be shared with JRG to help increase understanding of process -  not all of it focus on void budget line.

JRG058 – working group reviewing information new tenants receive – target date now 31/12/23.

JRG067- briefing on rent model to be re-issued.

JRG069 –Alan still investigating and will give update asap.

JRG070 – Void template updated with Council Tax costs and previous years spend.

JRG071 – confirmed that 100% Council tax paid as soon as a property void and 200% paid after a year if property still empty.

JRG072 – details of 3 new posts provided

JRG073 –Relates to overspend on mobile phones as costs higher than assumptions from last year.

Updated template for monitoring of void budget performance

Jane shared void template on screen.

Nicola ran through the update void info. Now down to 205 voids, is an overspend but number of voids repaired and returned increased significantly. With void numbers reducing rent loss and Council Tax expenses will reduce too. Spend on voids still an issue and number of factors at play- using agency workers, increase in material costs and been targeting longer term voids which had more work needed.

Still challenges in terms of meters – Help to Move helping clear debt and getting new meters fitted but engineer availability still an issue. Dashboard in use to monitor voids closely and have daily meetings about properties ready to let. Particularly high cost voids look at how they were terminated and the circumstances. Also monitoring refusals and doing pre-termination visits – are getting less voids costing more than £1500 to relet.

Décor pilot in Clydebank ongoing to give tenants more control over décor and reduce décor costs and void times.

Average relet times have increased as more longer term voids were relet. Also higher number of terminations in August but no particular trend.

Number of decants have been reduced but still too high. Now have a robust internal system to monitor them closely.

Martin added that had been using a sub-contractor when void numbers were high but now in position to do all internally. Still use back-up contractors if short of a particular trade. Also looking at clear-out costs and how they can be reduced.

Gurpreet asked how many voids were being delayed due to meter issues and Nicola agreed to confirm the figure.

Gurpreet also asked about tenancies ending due to evictions and ending in homeless accommodation and if that was a trend? John confirmed that has been an increase in homeless presentations but not seen an increase in people presenting from social landlords but been an increase in private tenants becoming homeless.

Gurpreet asked about decants and in particular about 2E West Court – Nicola will check out and advised that had been a resource issues but new manager Craig Wilson started a new process and this increased control has helped process decants more efficiently so should see an improving picture.

Gurpreet asked for an update on the Scottish Government funding for housing Ukranian refugees and John confirmed  been in dialogue with SG and putting in an funding application in next few weeks. Looking at 14 properties and applying for £200k– complex application process and will keep JRG updated on outcome.

Action: Nicola to confirm number of voids held up due to meter issues.

Action: Nicola to check out position re 2E West Court

Update on Capital Programme

Jane shared updated Capital programme on the screen.

Alan confirmed that most programmes progressing well. Costs are being closely monitored as spending trend is way ahead of targets. No questions raised.

Annual update on Owners Charter and the cost to the HRA

Costs for communal and improvement repairs are recovered from owners and the Owners Charter ensures that owners get regular updates on costs and can budget for what the final bill will be. Can be a delay in Capital work being billed as wait until after the defects period. The Owners Charter says that final bill won’t vary by more than 5% and this annual report is to monitor what the cost is to the HRA as any amounts over the 5% variation can’t be recharged.

Have a robust process in place to ensure that there are updates and to minimise any cost to the HRA and costs have been coming down.

Alan did flag that in 22/23 no bills were being issued due to a system failure and hadn’t been reactivated post pandemic. Being issued now and giving people more time to pay but likely be an increase cost to HRA for 23/24 period.

Rent Setting Consultation Plans

John confirmed that had wanted to start rent setting consultation in September but a range of factors delaying that and main one is the completing of the HRA estimates which won’t be ready until end of October. Also loans being renegotiated and don’t know cost yet. Operating in a more volatile financial climate so doing estimates too early affects robust calculations. Still opportunity to start consultation and proposing doing workshops about possible rent options. John suggested using the tenant JRG scheduled for 5/10 to get tenants discussions started on what their priorities would be and what opportunities for efficiencies there are.

Aberdeen City Council only one Local Authority to launch consultation so far and consulting on 6.3% and 8.8% -  John will share as much info as possible on other landlord rent consultations.

Agreed to avoid the school October week and start on 5/10 - dates of further meetings can be agreed by those who attend.

Action : Rent Option discussions to be prioritised and meetings set up  (John/Jane)

Dates of Next Meetings

Tenant JRG/ Rent Option discussion  5 October, 10 am Church St plus  zoom

Full JRG 23 November, 10am on zoom

Joint Rent Group

 Thursday 8 June 2023, 10am via zoom.

Attendees

Harry McCormack (tenant volunteer), Frances McGonagle (tenant volunteer), June Todd ( tenant volunteer), Nicola Pettigrew (Housing Operations Manager), Laura Ann Paton ( HRA Accountant), Alan Young (Housing Asset Manager), Jane Mack (Snr Housing Dev Officer), Councillor Gurpreet Johal (Housing Convener) and John Kerr ( Homelessness & Housing Development Manager).

Welcome and Apologies

Gurpreet welcomed everyone to the meeting. Jane advised that apologies been received from Janice Rainey (Finance Business partner), Martin Feeney (Building Services Manager) and Cllr Sorrell.

Updates on outstanding actions – copy of updated actions circulated ahead of meeting 

Jane shared document on screen and the updates on actions discussed.

JRG053 Make more use of Revenue Budget Matrix – Laura Ann confirmed that is being looked ahead of this year’s budget setting so that it can be made use of.

JRG055 – been confirmed that no access cards are still left when a tradesperson calls and no one in. Text process still to be implemented via IHMS team.

JRG067 –current rent model based on size. Main change is new builds and introduction of new house types like town houses. John suggested that he re-issue the briefing note previously done on the current model and JRG can then decide if a review is necessary.

JRG068 – Gurpreet disappointed that dates for Additional Capital Investment short life working group still to be confirmed – initial proposed date clashed with TPAS conference that number of tenants are attending. Discussed possible dates and agreed on Monday 19 June, 10am and any further meeting dates can be agreed then.

John will send out invites and a terms of reference for the group and Jane will arrange transport for those attending.

Updated template for monitoring of void budget performance – copy circulated ahead of meeting

Void performance shared on screen – quarter 4 financial updates been added since last meeting though void rent loss figure is for the whole year. Nicola also advised that operational voids now down to 194 and also have 86 voids classed as needing major work. Satisfaction with the relet standard has gone down and is an area being looked into and want to link in with TP and tenants to increase the number of surveys completed. Been a change in how the surveys are gathered and returns are lower so not very representative.

Nicola confirmed that the Budget overspend is due to the volume and amount of work being needed is high. Have been looking at the voids needing extensive work and meeting with Building Services and also looking at background of void – how it was terminated, was a pre-inspection done etc.

Been using additional contractors to help reduce numbers so that has increased costs but looking at cost variances across areas. Have regular meetings about the void budget and it is closely monitored.

Harry asked about the extensive work needed in some properties and how much of that is in the void figures. Nicola confirmed that they do categorise voids to identify major work, fire damage, structural issues so can account for the different levels of work needed – can also be a combination of factors.

Frances raised continued concern about decants and them not being looked at but is still rent loss. Nicola advised that staff are working on them and working with Building services to get them worked on.

Ongoing meter issues too - now have Help to Move assisting to clear meters and deal with faulty meter but still challenges as there is a national lack of engineers to repair meters which causes delays. Have recruited 2 new officers to help with these issues.

Repairs performance info – including cancellation figures Q4 ( JRG055) – copy circulated ahead of meeting

Quarter 4  figures seen at last meeting apart from appointments kept figure been updated. Quarter 1 for 2023 not available yet. No further questions on Q4.

Update on Capital programme – copy of updated programme circulated ahead of meeting

Late circulation of updated Capital programme so shared on screen and Alan talked through the update. Roof completions lower than predicted due to protracted communications with owners to get them on board. Been an underspend for most of year in window programme but now getting more done with new contractor and making good progress.

Been a spike in the heating budget as costs have increased but also more are being referred for renewals as increase in parts being obsolete. Has been an increase in costs across all programmes same as inflation affecting everyday costs.

Date of Next Meetings

Tenant JRG, 17 August, 10 am on zoom

Full JRG 28 September, 10am on zoom

Should also be some pre- rent setting discussion dates announced

Joint Rent Group

 Thursday 20 April 2023, 10am via zoom.

Attendees

Harry McCormack (tenant volunteer), Frances McGonagle (tenant volunteer), June Todd ( tenant volunteer), John Kerr ( Homelessness & Housing Development Manager), Janice Rainey (Finance Business partner), Martin Feeney (Building Services Manager), Alan Young (Housing Asset Manager), Suzanne Marshall (Housing Area Co-ordinator), Jane Mack (Snr Housing Dev Officer) and Councillor Gurpreet Johal (Housing Convener).

Welcome and Apologies

Gurpreet welcomed everyone to the meeting. Jane advised that apologies been received from Nicola Pettigrew (Housing Operations Manager), Laura Ann Paton ( HRA Accountant) and Cllr Sorrell.

Updates on outstanding actions – copy of updated actions circulated ahead of meeting 

Jane shared screen and the updates on actions discussed.

JRG053 – Janice advised that matrix is cumbersome and time consuming to use – wants to discuss internally how to do easier. Committed to doing draft budgets early and make process more transparent so hoping for draft budget in August.

JRG055- Martin advised that is still being progressed and apologised for the delay. Existing process is still being followed and jobs get cancelled down after 2 no accesses. Couldn’t give a definite date when texting process will be in place but is being prioritised.

JRG060-Frances raised concern about the delay in identifying that these recharges hadn’t been made and that will be difficult to pursue people for recharges from 3 years ago. Janice echoed those concerns and explained that as recharges fluctuate it’s difficult to see even when budget monitoring is done. Have a new system in place now and won’t happen again. Janice agreed that will be more difficult to recoup the money but in normal circumstances have a low recoup level – would only expect £10k so at least not a massive impact on HRA income.

JRG062- Martin advised that not got a cyclical programme in place but being developed on housing system. Are working from spreadsheets so cyclical work like gas checks are getting done. Vent and extractor fan being pulled together to capture a programme for the multi-story flats in the first instance as they have kitchen and bathroom fans. Difficult to get info on other properties. For the flats will text tenants to say in their area that week – should start in June /July. Longer term plan is do the development work on QL for cyclical work and be able to publicise them.

Gurpreet raised his concern about the delay in the programme being implemented and Martin disappointed too but other cyclical works are still getting done.

Updated template for monitoring of void budget performance – copy circulated ahead of meeting

Void performance shared on screen and Suzanne summarised the performance. Void budget figures for Q4 not available. Number of voids is down to 310 but performance targets not met. Satisfaction with the relet standard down to 40% but only 10 surveys completed – working to increase number of surveys completed to get more representative figures. Also analysing negative comments to see where improvements needed. Number of decants increased due to results of heavy frost and cold weather.

Frances raised concern about decants lying empty with no work being done to them – Suzanne confirmed that do monitor decants and get updates on them. Also offer to stay on in decant if decanted for more than 6 months. Martin advised that shouldn’t be no work getting done – do prioritise voids and are building resilience and recruiting more staff to help catch up with demand.

Gurpreet welcomed improvements but still number of examples of voids lying empty – Suzanne advised could be a number of reasons and would need specific addresses to investigate. Meter issues have caused delays but since Feb been using Help to Move which has improved process though still some meters they can’t deal with but have been a massive help.

Repairs performance info – including cancellation figures Q4 ( JRG055) – copy circulated ahead of meeting

Repairs performance shared on screen and Martin talked thro ’performance figures. Been an increase in repair requests which meant some targets not met – annual fluctuation due to weather. Working hard on reducing no accesses and some instances when turn up on wrong day but being worked on. Gurpreet pointed out the increase in number of no accesses and concern that shows systematically not working and not seeing improvements. Martin advised are drilling down in the stats and dealing with identified issues. Is a cost to Building Services as well as disruptive to tenants so Martin too keen to ensure improvements happen – is a high priority for Building services and expects improvements to show in 2023/24.

Monthly meetings between Martin and Nicola take place so communication between teams is happening and a key are of joint working. Suzanne also confirmed that monthly reports on no accesses are shared with HO’s so that they can contact tenants to resolve.

Update on Capital programme – copy of updated programme circulated ahead of meeting

Capital programme update shared on screen and Alan summarised progress – generally most programmes going well – some resource issues with door/ window programme.

Frances asked question about why such a high overspend in the Minor work budget and Alan said that budget is set at historical levels and comes from work that is revenue work but when goes over a certain level gets moved into capital budget- eg some fire damage properties, back court upgrades- retaining wall repairs needed and ends up being expensive and not suitable for environmental upgrade budget.

Additional Capital Investment Proposed Tenant/Officer Task and Finish Group

John updated that a paper going to the Housing & Community Committee on 3/5 – just been published and sets out the rent increase option of 5% which generated additional £50m for investment. £10m is to scale up Buyback scheme with a focus on larger family homes much needed. Also includes plans to introduce and accelerate response to dampness and mould. Includes using proactive technology to use sensors to identify dampness and mould before it becomes a problem.

Tenant priorities identified in the rent setting consultation focused on energy efficiency, kitchen/bathroom renewals and window/door renewals and these will be main focus.

Want to establish a short life working group with tenants and officers to discuss possible programmes and ensure that tenant voices are being heard. Want to get meetings started in May and John asked if there was agreement to proposal and if timescale was doable.

Frances asked for reassurance that were going to listen to tenants and John confirmed yes and was committed to delivering on tenant priorities. June reminded that the £50m wasn’t what majority of tenants wanted and still concerned about rent levels.

Tenant volunteers agreed that they wanted the invite opened up to all tenant groups to get a range of voices and John agreed to writing up a terms of reference for the short life working group and send out with an invite to all TRA and scrutiny panel  members.

Agreed JRG would be good place to monitor progress of the additional investment programmes once they been agreed.

Date of Next Meetings

Tenant JRG, 18 May,10 am on zoom

Full JRG 8 June, 10am on zoom

Joint Rent Group

 Thursday 16 February 2023, 10.30am via zoom.

Attendees

Harry McCormack (tenant volunteer), Frances McGonagle (tenant volunteer), John Kerr ( Homelessness & Housing Development Manager), Laura Ann Paton (HRA Accountant), Martin Feeney (Building Services Manager), Alan Young (Housing Asset Manager), Suzanne Marshall (Housing Area Co-ordinator), Jane Mack (Snr Housing Dev Officer) and Councillor Gurpreet Johal (Housing Convener).

Welcome and Apologies

Gurpreet welcomed everyone to the meeting. Jane advised that apologies been received from Nicola Pettigrew (Housing Operations Manager), June Todd (tenant volunteer) Stefan Kristmanns (Housing Dev Co-ordinator) and Cllr Sorrell.

Updates on outstanding actions – copy of updated actions circulated ahead of meeting plus JRG058 Briefing note on relet standard 

Jane shared screen and the updates on actions discussed.

JRG061 –happy with update and to mark action as complete as will continue to monitor void performance through regular updates of the void monitoring template at each full JRG meeting. Gurpreet also gave reassurance that voids being looked at in detail and a key delay with voids was problems getting power back on for new tenant and this was being prioritised – Suzanne confirmed that they have an agreement with ‘Help me move’ to assist and training to take place in next few weeks and will help them resolve such issues quicker. Also 2 additional support officer posts being created and advertised to help new tenants.

JRG058 Briefing note on relet standard – Suzanne summarised the briefing note and the process undertaken to review the relet standard and the changes proposed. Changes to be monitored for initial 6 months to ensure they work.

Outcome of rent setting consultation – briefing note circulated ahead of meeting

Jane shared screen and gave a summary of the consultation results. The preferred option is the 4% increase and that is being recommended - decision still to be made by Councillors on 1/3.

Updated template for monitoring of void budget performance – copy circulated ahead of meeting

Void performance shared on screen and Suzanne summarised the performance. Void budget overspend due to volume of current voids. Number of properties been relet has increased (up to 204) but other performance targets not met. Work continues to focus on voids – monitored daily and working closely with Building Services.

Repairs performance info – including cancellation figures Q3 ( JRG055) – copy circulated ahead of meeting

Repairs performance shared on screen and Martin summarised progress. Narrowly missed target for emergency repairs in that quarter – January figure was 5.49 hours so back in target. When repairs completed out of target means they also miss the Right First Time (RFT) criteria. Number of appointments kept is up and met target. No access cancellations have continued to increase – texting hasn’t started yet but being tested and should be live in next week or so. Gurpreet raised a constituent query he was dealing with where Building Services had called out but not on the appointment day – could be a typo in response and Martin’s team investigating.

Update on Capital programme – copy of updated programme circulated ahead of meeting

Capital programme update shared on screen and Alan summarised progress – generally most programmes going well. Windows and doors behind schedule but now have back up support in place but this delay will take time to catch up. Any underspend on budgets gets carried forward. Has been an increase in material costs so within certain budgets will be able to deliver less numbers than originally costed. Overspend on heating upgrades been due to demand for new boilers being higher than predicted- often can’t source parts so need to replace boiler rather than leave people without proper heating.

Review of Capital programme– JRG064- JRG to be kept informed of progress of review and include JRG members when considering tenant priorities.

  •  Capital Programme 23/24 – Alan
  •  Housing Asset Management Strategy Update – John

Capital Programme 23/24 – Alan confirmed that the annual programme was based on what was needed to replace elements reaching end of life cycles and to ensure we meet current EESSH and SHQS. Tenants’ priorities identified in the rent setting aligned with what officers had identified and are the key areas they are focusing on – energy efficiency measures, kitchen and bathroom renewals and window/door renewals. Continuing too with External Wall insulation (EWI) programme and had good tenant feedback not just on the improved insulation but on the improved look of buildings.

Refresh of Capital programme starts with potential rental income and condition surveys identify what needs to be done and work out from there what can be accommodated in the programme. Number of kitchens and bathrooms needed been identified and looking at scope to increase capacity or move budgets about to accommodate. Core capital programme are all essential items plus additional improvement investment.

Housing Asset Management Strategy update – John confirmed that the current Strategy was approved in 2018 so in final year and due to be refreshed. Plan is for new Strategy to go to November HACC.

2 key documents will inform the Strategy and one is Scottish Government/ Housing Regulator Asset Management Guidance and Standards – not published yet but critically will include EESSH 2 review which will have a huge impact. Target for EESSH 2 is 2032 and key challenge will be how that is met and how rents can be kept affordable. All Councils and Housing Associations will be in similar situation and concerns raised about 2032 target as other Net Zero targets are 2045 so putting additional pressure on social landlords.

Previous review of Asset Management review included an overview at Liaison meeting and John happy to do that again and wants as many tenant voices in the Strategy as possible- timing dependent on when SG/Hsg Regulator Guidance and Standards published and will develop tenant involvement from there.

Gurpreet raised the consultation on the Additional Dwelling Tax which includes a proposal to make Council’s exempt the same as Housing Associations. Harry confirmed the WDTRO have responded and Jane has circulated to wider TRA  and scrutiny panel members.

Date of Next Meetings

Tenant JRG 16 March, 10 am on zoom

Full JRG 20 April, 10am on zoom